DAF systems and equipment

Dissolved air flotation plant from 2 to 1,200 m³/h, in four configurations. The right one is decided by flow, by how much civil work the site can absorb, and by how aggressive the effluent is.

Direct answer

DAF systems fall into four types. Packaged skid units (2–150 m³/h) arrive pre-piped and pre-wired and need only a level slab — the default for single industrial sites. High-rate cells (200–1,200 m³/h) run at 15–30 m/h for municipal works and large industrial duty. Containerised plant (5–60 m³/h) puts the whole treatment train inside a 20 or 40 ft shipping container for remote or temporary sites. Circular flotation cells suit sludge thickening and large-diameter municipal duty. Every configuration shares the same three sub-systems: a saturator and recycle loop, a coagulation and flocculation stage, and the flotation cell with skimmer.

Choose by flow and site constraint

Capacity and footprint table

Model classFlow m³/hFlotation area m²Overall footprintInstalled powerTypical duty
Micro packaged2 – 100.4 – 1.52.2 × 1.2 m2 – 4 kWCar wash, small dairy, laundry
Small packaged10 – 301.5 – 43.5 × 1.6 m4 – 9 kWAbattoir, small food plant
Medium packaged30 – 804 – 116.0 × 2.2 m9 – 20 kWBrewery, edible oil, tannery
Large packaged80 – 15011 – 209.5 × 2.6 m20 – 35 kWLarge food plant, paper saveall
High-rate cell200 – 50010 – 257.0 × 4.0 m35 – 70 kWMunicipal, WWTP uprating
High-rate, multi-cell500 – 1,20025 – 60Site specific70 – 160 kWLarge municipal, surface water
Containerised5 – 601 – 820 or 40 ft ISO6 – 25 kWRemote, temporary, rental
Footprint is the skid envelope and excludes access, chemical storage and sludge handling. Allow 1 m clear on three sides and 1.5 m on the skimmer drive side. Flotation area assumes conventional loading for packaged units and 20 m/h for high-rate.

What is on a complete skid

  • Flotation cell with inclined plate or open flotation zone, adjustable effluent weir and sludge hopper.
  • Surface skimmer — chain-and-flight or rotating blade, variable speed, with a bottom scraper where settleable solids are present.
  • Saturator — pressure vessel at 4–6 bar with packed or unpacked contact section, level control, safety relief and air injection.
  • Recycle pump — multistage centrifugal, sized on the calculated recycle flow at saturator pressure, not on a percentage rule of thumb.
  • Air supply — oil-free compressor or blower with receiver, dryer and pressure regulation.
  • Release nozzles or needle valves — the component that determines bubble size distribution and therefore performance.
  • Coagulation and flocculation stage — inline static mixer or stirred chambers with 1–3 min flocculation at G of 30–70 s⁻¹.
  • Dosing skid — coagulant, polymer make-up and dosing, pH correction, all with calibration columns.
  • Control panel — PLC with HMI, level and pressure instrumentation, optional pH and turbidity monitoring, remote access.

Materials of construction

Materials are selected against your effluent, not against a price list. This is the specification decision with the largest effect on whole-life cost, and the one most often compromised to win a price comparison.

MaterialUse whereAvoid whereRelative cost
Carbon steel + epoxyNeutral pH, chloride <200 mg/L, municipal, brewery, paper effluentAny acid or chloride exposure1.0
SS304Food, dairy, general industrial, warm waterChloride >200 mg/L, pH <41.3 – 1.5
SS316LEdible oil, textile, chloride to ~5,000 mg/L, low pHChloride >5,000 mg/L at elevated temperature1.6 – 1.9
Duplex 2205Tannery, mining, produced water, high chlorideRarely — cost is the constraint2.2 – 2.8
GRP / FRPChemically aggressive, corrosive vapour, coastal sitesHigh mechanical loading, UV without gelcoat1.2 – 1.8
Concrete + liningLarge municipal cells, permanent installationsWhere speed of delivery mattersSite dependent

Scope of supply and delivery

Standard scope covers process sizing and design, the flotation unit with saturator and recycle system, the coagulation and flocculation stage, dosing skid, control panel and instrumentation, documentation (general arrangement, P&ID, foundation loading, electrical schedule, O&M manual, commissioning procedure), and commissioning support on site. Delivery is CIF to any African port.

Installation is normally executed by a local contractor to our drawings, which keeps mobilisation cost and time down. Full scope of services →

Frequently asked questions

What is the difference between conventional and high-rate DAF?

Surface loading rate and internal hydraulics. A conventional DAF runs at 5–12 m/h in an open rectangular flotation zone. A high-rate unit runs at 15–30 m/h using engineered inlet distribution and often inclined plates in the separation zone to maintain the bubble blanket at higher velocity. High-rate gives two to three times the throughput per square metre but is less tolerant of variable influent and needs more attentive chemical control.

How much space does a DAF need?

A 30 m³/h packaged unit occupies roughly 3.5 × 1.6 m of skid, and about 6 × 4 m including access, chemical storage and the dosing skid. A 500 m³/h high-rate cell occupies about 7 × 4 m of tank and 12 × 9 m of plant area. Both need a balance tank upstream, which is often the larger structure — and the one most frequently omitted from a supplier’s footprint drawing.

What is the lead time for a DAF unit?

Typically 8–14 weeks from order for packaged carbon steel or SS304 units, 12–20 weeks for stainless and duplex, and longer where the control philosophy is bespoke. Sea freight to an African port adds 3–7 weeks depending on routing. Jar testing and process confirmation should be complete before the order is placed, not during manufacture.

Can a DAF be rented rather than bought?

Containerised units are suited to rental and short-campaign duty — mine site dewatering, construction, a factory bridging a compliance deadline, or a pilot before committing to a permanent plant. The economics generally favour purchase beyond about twelve to eighteen months of continuous operation.