Packaged DAF units, 2 to 150 m³/h

The workhorse of industrial pretreatment: a complete flotation plant on one frame, pre-piped and pre-wired, needing only a level slab, a power supply and pipework.

Direct answer

A packaged DAF unit is a factory-assembled, skid-mounted dissolved air flotation plant covering 2 to 150 m³/h. It carries the flotation cell, surface skimmer, saturator, recycle pump, air compressor, flocculation stage, dosing skid and control panel on a single frame. Because it needs no civil structure beyond a level reinforced slab, typical installation takes three to seven days against three to five months for a civil-built cell. Surface loading is 5–12 m/h, installed power 2–35 kW depending on size, and delivery is by flatbed or open-top container.

Capacity table

Flow m³/hFlotation area m²Skid L × W × HDry weightOperating weightInstalled power
2 – 50.4 – 0.72.2 × 1.2 × 2.0 m0.6 t2.0 t2.2 kW
5 – 100.7 – 1.52.8 × 1.4 × 2.1 m0.9 t3.2 t3.0 kW
10 – 201.5 – 2.83.5 × 1.6 × 2.2 m1.4 t5.0 t5.5 kW
20 – 402.8 – 5.54.6 × 1.9 × 2.4 m2.3 t8.5 t9.0 kW
40 – 705.5 – 9.56.0 × 2.2 × 2.6 m3.6 t14 t15 kW
70 – 1109.5 – 157.8 × 2.4 × 2.8 m5.2 t22 t22 kW
110 – 15015 – 209.5 × 2.6 × 3.0 m7.0 t31 t30 kW
Indicative envelopes for carbon-steel construction at 7.5 m/h surface loading. Actual dimensions depend on the design loading rate for your stream, materials and whether the dosing skid is integrated or free-standing. Units above roughly 60 m³/h usually ship as two or three sections for road transport.

Scope of supply

What the site must provide

ItemRequirementCommon mistake
FoundationLevel reinforced slab, 150–250 mm, designed for operating weight plus 25 %Slab sized on dry weight
Balance tank6–12 h HRT, mixed, with level controlOmitted entirely — the single most common cause of poor performance
Screening1–3 mm fine screen upstreamCoarse screen only; fines wreck the recycle pump
Power3-phase, per installed power; stable supply or generator backupNo allowance for compressor inrush
WaterClean water for polymer make-up and wash-downPolymer made up with raw effluent
Sludge routeHolding tank, minimum 2 days, then dewatering or tankerAssuming the DAF sludge hopper is storage
Access1 m clear on three sides, 1.5 m on the skimmer drive sideUnit boxed in against a wall
DrainageBunded chemical area with separate containmentChemicals stored on open ground

Indicative price bands

Ex-works equipment only, complete with dosing skid and controls, carbon steel with epoxy lining. These are planning figures for budget purposes, not quotations.

FlowCarbon steel + epoxySS304SS316L
2 – 5 m³/hUSD 18,000 – 32,000+35 %+70 %
5 – 20 m³/hUSD 25,000 – 60,000+35 %+70 %
20 – 60 m³/hUSD 60,000 – 140,000+30 %+65 %
60 – 150 m³/hUSD 140,000 – 350,000+30 %+60 %
Excludes freight, insurance, duties, local installation, balance tank, screening and sludge dewatering. Duplex 2205 typically runs 120–180 % above carbon steel. Prices move with steel and stainless surcharges; treat these as orders of magnitude and request a quotation for anything committed.

Frequently asked questions

How long does it take to install a packaged DAF?

Three to seven days on a prepared slab for a single-piece skid: set down, connect inlet, outlet, sludge and drain, terminate power, fill and level. Multi-section units in the 60–150 m³/h range take one to two weeks to assemble. Commissioning — leak test, saturator pressurisation, jar-test confirmation, dose optimisation and operator training — adds a further three to five days.

Do I need a balance tank before a packaged DAF?

In almost every industrial application, yes. A DAF is a steady-state device: it wants constant flow, constant solids and stable pH. Industrial effluent is none of those things. Six to twelve hours of mixed balancing turns a difficult stream into an easy one, and it is by a wide margin the cheapest performance improvement available. Omitting it to save capital is the most expensive decision made in effluent plant procurement.

Can a packaged DAF be moved later?

Yes — that is one of its advantages. A skid unit can be drained, disconnected and relocated in a few days, which suits leased premises, phased factory expansion and businesses that expect to move. Civil-built cells cannot. Factor the operating weight into any crane or transport planning.

What maintenance does a packaged DAF need?

Daily: check float thickness and effluent clarity, confirm chemical levels, log saturator pressure. Weekly: clean release nozzles, check skimmer flights and chain tension, calibrate dosing pumps. Quarterly: inspect the saturator internals, service the compressor, check the recycle pump. Annually: drain and inspect the cell, check coatings and weld lines. Budget 0.5–1 operator-hour per day for a mid-sized unit.